Saver
Profile (slot)
1.1 Slot cutting - Dimension in accordance with design
(depth, vertical spacing of slots)
1.2 Slot clearances - Vacuum out the slot and flush with water -
temperature over 0°C (cohesive force)
1.3 Preparation of bars (admeasurements, calculate
with overlap
of bars
- 500 mm)
1.4 Preparation and mixing of grout (2 x 2 components
- liquid and dry powder
- don't water down)
1.5 Using the grout gun and grouting into the back of slot
1.6 Inserts of bars and push back into grout
1.7 Grouting, coverage ratio
1.8 Multiple reinforcing bars if required
Saver Profile - Bars in pre-hole
2.1 Drill holes - Dimension in accordance with design
(depth, diameter of drill
holes)
2.2 Holes clearance - Vacuum out the holes and flush with water
temperature
over 0°C (cohesive force)
2.3 Preparation of bars, grout and grout gun with nozzles
- admeasurements,
mixing (length of holes and Brutt anchors, diameter
of holes)
2.4 Applications of ties with grout gun and nozzle - depending
upon material
and the length of tie
|
 |